Construction Activities Estimated Timeline

For more detailed information, see the following attachments:

To see up to date photos, click here to view the photos on our Facebook page.

Concord Facebook Page

Estimated Completion Date:  mid-November 2017

Screen Shot 2017-02-13 at 1.10.59 PM

West Foyer Addition

Roofing is nearly complete.

HVAC ductwork is being installed.

Exterior Dryvit will be starting this week.

Fire protection rough-in is ongoing.  The 3 hour fire wall is 98% complete.

Construction workers have built a temporary partition at the second floor leading to the new vestibule. This will allow workers to continue to remove the existing exterior wall and prepare the opening for finishes.

Glazing being measured and ordered.

Bathroom- Fellowship Hall

Slab has been removed.  The slab should be re-poured this week.

Plumbing lines are being installed.

Children’s Stairwell

Contractor is staining the doors offsite. they should be ready to hang soon.

Final touches are being completed.

Updated as of August 28, 2017